Baldwin Diesel Exhaust Stacks

By Matthew Imbrogno

All Baldwin photos unless noted

Initially, both VO models had one exhaust stack just in front of the cab, with a single muffler mounted above the generator.
Single Stack On early VOs (left) the stack was flush with the top of the hood, on later VOs (right) the stack was taller Single Stack close up

This continued until 1944, when it was found that the single muffler and exhaust created backpressure, restricting the flow of the exhaust and retaining heat. The excess heat generated so close to the electrical system caused it to overheat and fail. This was addressed with a new exhaust manifold. This took the form of 2 separate manifolds each with its own stack, creating the dual stack variety. On the VO660, there were 3 cylinders per stack. On the VO1000, there were 4 cylinders per stack.
CNW 1237 Dual stack VO660
DTR 101 Dual stack VO1000

While this removed the problem of overheating the electrical system, it still restricted the flow of the exhaust. Thus another change was made. On the VO660, this was done by simply adding another stack to each manifold to relieve the pressure. On the VO1000, 4 separate manifold sections were installed serving 2 cylinders each. This led to the 4 stack variety. The VO660 had 2 groups of 2 stacks spaced close together, but the VO 1000 had the four stacks spaced evenly apart.
LIRR 403 - BLW  13075.1 Four stack VO660
Wabash 304 Four stack VO1000
No VO-660s were delivered with 3 stacks, but some were created by the railroads own shops. On roads that had both types of VOs, some 660s had their two 3 cylinder manifolds replaced with three 2 cylinder ones off the VO1000s. This is very rare however, as Baldwin was happy to supply replacement parts for engines with the older style exhausts.

Later, on the DS and S series switchers, Baldwin adopted the 3 stack setup as standard for the smaller normally aspirated type, and a single stack for the bigger turbocharged units.
CNW 1260 Three stack normally aspirated DS4-4-660
S12 Single stack turbocharged S12

As a side note, 4 stacks was not the limit on the varieties. Some railroads gave their units a separate stack for each cylinder, creating 6 and 8 stack models with a solid row of pipes above the engine. Baldwin called this practice "Hotrodding", in reference to the way people tricked out muscle cars.

Six stack VO660
IMM 1953
photo by: Keith Ardinger
Avalos Mill, 1975
Six stack DS4-4-660
Napa Valley
photo by: Thomas Hillebrant
Portola, CA - July, 2007
Six stack DS4-4-750
Weyerhaeuser 101
photo by: Nicholas Todd
Klamath Falls, OR.-July 15, 2011

Six stack S8
Medco 8
photo by: John Powell
June 2011
Eight stack VO1000
US Steel 12
photo by: Richard Adams
Superior, WI - July 27, 1979
Eight stack VO1000
Colorado & Wyoming 1107
photo by: Robert A. Willis
Dallas, TX - 2005


Seven stacks ?

There is one other oddball in the mix: Magma Arizona Railroad #9. This S-8 switcher was built for McCloud River RR as their #31. It was made as an S-8 that could be upgraded to an S-12 with the addition of a turbocharger. Thus, it had a single exhaust stack above the generator. When it was transferred to Magma, somehow the hood roof of another S-8 with 6 stacks was swapped out with its original hood. These stacks are dummies, as the manifold is still routed to the single large stack. Thus, it is the only Baldwin switcher, or any other locomotive I know of for that matter, to have 7 smoke stacks!
Magma Arizona  9
photo by: Ted Ellis
collection of Mark Laundry

April 18, 1988 - Magma Jct., Arizona
Magma #9 an S8 with seven separate stacks. The active single stack on #9 can just be seen between the bell and the row of six separate stacks.





Matthew Imbrogno, a frequent contributor, originally posted this text to the Classic Trains Forums


  • back to the table of contents page